Phase A — First server runbook (to live listing)

Goal: One 4× A100 (40GB or 80GB) server live in colocation, financed per term sheet, listed on Vast.ai (verified path), with insurance and ≥6 months fixed-load reserve.

Canonical strategy: BUSINESS-PLAN.md §9.0, §10, §14.


Before you spend money (gates)

# Gate Pass criteria
G1 Entity + tax UG (or agreed structure) + Regelbesteuerung if Steuerberater recommends Vorsteuer path
G2 Colo quote Signed or firm: space, kW, remote hands, IPv4, SLA, exit terms
G3 Finance quote Payment, term, early buyout, personal guarantee scope (minimize / cap)
G4 Hardware quote 4× GPU + server BOM; native PCIe confirmation (see 01-GPU-RFQ.md)
G5 Unit economics Rebuild §9.0 with your colo + your monthly payment; confirm go thresholds
G6 Liquidity Bank balance plan: ≥6 months of (colo + insurance + maintenance + financing) after any down payment

Week-by-week sequence (typical)

Weeks 1–2 — Structure and RFQs

  1. Steuerberater brief (entity, VAT, depreciation intent).
  2. Send GPU RFQ (DE/EN per supplier table in RFQ doc).
  3. Send colo RFQ (02-COLO-RFQ.md).
  4. Parallel (low intensity): Christine shortlists 2–3 RE sites for Phase C (no binding capex).

Outputs: Comparable colo + finance + hardware offers; updated §9.0 spreadsheet.

Weeks 3–4 — Contracting

  1. Pick colo + finance + supplier; legal skim on default, termination, buyout, SLA credits.
  2. Order hardware (align delivery with colo ready date).
  3. Elektronikversicherung + Betriebshaftpflicht bound before rack power-on.

Outputs: Signed contracts; insured asset schedule; install date.

Weeks 5–6 — Build and ship

  1. Assemble or receive integrated server; burn-in (stress + nvidia-smi, ECC/Xid watch).
  2. Ship / deliver to colo; label assets; IPMI + OS baseline documented.

Outputs: Burn-in log; access checklist (IPMI, SSH, monitoring).

Weeks 7–8 — Rack and network

  1. Install per provider; PDU / dual feed check; link up; latency smoke test.
  2. Backup access path (provider console / KVM).

Outputs: Rack photos (if required); network diagram; monitoring alerts.

Weeks 9–10 — Marketplace

  1. Vast host onboarding; verified checklist (drivers, persistence, templates).
  2. Listing copy + initial price band from latest snapshot methodology (tooling/marketplace/).
  3. Soft launch pricing → tune on realized net EUR/GPU-h and occupancy.

Outputs: Live listing; daily dashboard: util, $/h gross, fees, incidents.

Weeks 11–12 — Decision checkpoint

  1. Compare 90-day (or minimum 60-day) rolling metrics to BUSINESS-PLAN.md Phase A goals.
  2. Hold / optimize / exit per stop-loss (§9.0): e.g. 2-month rolling net < -€400/mo → freeze expansion.

Documents and tools (repo)

Item Path
BOM + price snapshot 03-BUYING-LIST.md
GPU first-offer RFQ 01-GPU-RFQ.md
Colo first-offer RFQ 02-COLO-RFQ.md
Unit economics snapshot 04-UNIT-ECONOMICS.md
Vast snapshots / reports tmp/market-snapshots/, build/vast_market_report.md (regenerate via tooling)

KPIs to track from day one

  • Occupancy (rented GPU-hours / available GPU-hours).
  • Realized net EUR/GPU-h (after platform fee + FX — define formula and stick to it).
  • Incidents (tickets, downtime minutes, provider faults).
  • Cash: colo + finance + insurance + maintenance vs revenue.

Post-live gates: 30 / 60 / 90 days

Use calendar days from first paid rental hour (or from listing verified live if you need a fixed start — pick one and keep it consistent).

Horizon Review focus Pass (typical) If fail
30 days Listing health, initial util, incident rate, net EUR/GPU-h vs model No extended 0% / dead listing; burn-in issues resolved; cash not breaching stop-loss alone Fix template, pricing, verification tier, colo network; pause any expansion talk
60 days Rolling 30d occupancy stabilizing; support backlog; provider SLA Occupancy trending toward ≥60% (or documented ramp reason); 2-month rolling net above stop-loss floor in §9.0 Root-cause: demand vs price vs reliability; adjust ops budget
90 days Rolling 60–90d economics; reserve vs 6-mo fixed load; Phase B readiness Meets Phase A goals in BUSINESS-PLAN.md §10; reserve still ≥6 months fixed load Hold scaling; execute remediation or exit per §9.0

These gates are in addition to the week-11–12 checkpoint above (whichever calendar matches your ramp).


When Phase A is “go” for server #2

See BUSINESS-PLAN.md §10 Phase B: reserve floor, DSCR-style stress, no new uncapped personal guarantees.